No. Section km Estimated

/contract value

Source of funding Percentage (%) of the project implementation Note
1 2 3 4 5 6 7
Sections under construction
1 Svilaj – Odžak, Phase II 10.4 77,250,000 EBRD 40 M€ Designing: 100% Main Design, works on Phase II mostly completed, except for the Border crossing Svilaj since a building permit is still not obtained, so it is expected for the works to be continued upon its issuance. If everything goes as expected, the works should be completed at the end of summer 2018.
Expropriation: 100%
Building: 75 %
2 Drivuša – Klopče 2.23 61,846,815 KFAED 10,5 M KD Designing: 100% Main Design, the construction of this subsection is almost completed. The time limit for completion of the construction is already prolonged,it is expected for the works to be completed in the mid-2018.
Expropriation: 100%
Building: 72.05%
3 Klopče – D.Gračanica    5.8

_____

204,732,177 OFID 24 M€

OFID48 M USD

EBRD 36 M€

Designing: 100% Main Design, work on this subsection are in progress. Due to extremely bad geologic conditions on the route, the time limit for completion of the construction will probably be slightly prolonged. The completion of works is foreseen in the mid-2019.
Expropriation: 100%
Building: 43.15%
Sections – construction planned to begin in 2018
4 Počitelj – Zvirovići 11 195,583,000 EIB 100M€ Designing: 100% Main Design; As recommended by the Bank, the tender procedure for selection of a contractor will be repeated. Upon its termination and if everything goes as expected,
Expropriation: 100%
Building: 0% the construction of this subsection should begin in 2018.
5 Vraca Tunnel – Pečuj Tunnel 3.9 113,438,140 EBRD 50 M€ Designing: 100% Preliminary Design – Yellow FIDIC. A tender procedure for selection of a contractor and an engineer is in progress.  Thetime limit for submission of tenders shall be 15 January 2018. Upon the tender procedure completion, signing of contracts and commencement of works is expected to take place in April or May of 2018.
Expropriation: 99%
Building: 0%
6 Počitelj – Buna 7.2 64,645,499 EBRD 30M€ Designing: 100% Main Design.  A tender procedure for selection of a contractor and an engineer is in progress.  Thetime limit for submission of tenders shall be 15 January 2018. Upon the tender procedure completion, signing of contracts and commencement of works is expected to take place in April or May of 2018.
Expropriation:

93,73%

Building: 0%
7 Ponirak – Vraca 2.66 161,670,864 EIB 50M€ Designing: 100% Main Design.  A tender procedure for selection of a contractor and an engineer is in progress.  The first phase (pre-qualification) is almost done. Upon completion of the second phase of the tender procedure, signing of contracts and commencement of works is expected to take place in April or May of 2018.
Expropriation: 93,37%
Building: 0%
8 Vranduk – Ponirak 5.3 98,597,926 OFID 49 M€ Designing: 90% Main Design.  A tender procedure (pre-qualification) for selection of contractors on this motorway subsection. Upon completion of this phase and submission of tenders, a contractor should be chosen and a Contracting Agreement should be signed in August 2018.
Expropriation:

74,61%

Building: 0%
9 Nemila – Vranduk 5.7 70,409,880 KFAED 36 M€ Designing: 70% Main Design. Project documentation for this subsection is being completed. Upon completion of preparation, call for tenders (pre-qualification) is planned for the end of May 2018. Upon completion of the tender procedure, signing of contracts and commencement of works is expected to take place in October or November of 2018.
Expropriation: 0%
Building: 0%
10 Kvanj Tunnel -Buna 5.2 203,778,471 EIB 100M€ Designing: 49% Preliminary Design – Yellow FIDIC. Project documentation for this subsection is being completed. Upon completion of preparations, call for tenders (pre-qualification) is planned for the mid-2018. Upon completion of the tender procedure, signing of contracts and commencement of works isplanned for the end of 2018.
Expropriation: 0%
Building: 0%planned for the end of May 2018
 

 

 

 

 

 

 

 

11

 

 

 

 

 

 

Tarčin – Ivan

 

 

 

 

 

 

 

6.8

 

 

 

 

 

196,560,915

 

 

 

 

 

EIB 50 M€

EBRD 50 M€

Designing: 97% Main Design completed – Access road needs to be designed.Upon completion of preparations, call for tenders (pre-qualification) is planned for the mid-2018.  Upon completion of the tender procedure, signing of contracts and commencement of works is planned for the end of 2018.
 

Expropriation: 95%

 

Building: 0%

 

 

 

 

 

 

 

 

12

 

 

EW Lašva – Nević Polje (Lot 1 Vitez – Nević Polje)

 

 

 

 

 

 

5.4

 

 

 

 

 

 

 

89,000,000

FBiH Government conclusion – clearing debt funds of the Russian Federation

 

 

 

 

 

Designing: 65%

Main Design completed – Access road needs to be designed and the current interchanges need to be adjusted to the Central Bosnia Canton Spatial plan. Upon completion of the project documentation, the tender procedure for selection of a contractor and an engineer would be carried out promptly (in June 2018). If everything goes as expected, the works could begin in September 2018.
 

 

 

Expropriation: 0%

 

 

Building: 0%

 

 

 

 

 

 

13

 

 

 

 

 

 

EW Prača – Goražde (Phase 1)

 

 

 

 

 

 

13.7

 

 

 

 

 

 

70,000,000

 

FBiH Government conclusion – funds from the profit of public enterprises

 

 

 

Designing: 100%

Preliminary Design completed – 5.5. km long tunnel will be constructed in accordance with D & B – Yellow FIDIC model. Upon the 2018 FBiH Budget adoption, the tender procedure for selection of a contractor and an engineer for construction of LOT 1, Phase II of this expressway, encompassing the excavation and primary tunnel support. If everything goes as planned, the commencement of works is planned for July 2018.
 

 

Expropriation: 0%

 

Building: 0%

 

 

 

14

 

 

 

 

EW Mostar – ŠirokiBrijeg

 

 

 

 

 

66

 

 

 

 

 

15,250,000

 

FBiH Government conclusion – funds from the profit of public enterprises

 

 

Designing: 10%

 

Development of the Main Design for 66 km is in progress. The first 4 km is being completed. The development of the Preliminary and the Main Design will be completed in 2018. If previous phases go as planned, the tender procedure completion and signing of contracts is expected to be done until the end of 2018.

 

 

Expropriation: 0%

 

Building: 0%

 

 

 

15

 

 

 

 

 

 

Sarajevo bypass

(Lot 3b)

 

 

 

 

 

1.6

 

 

 

 

 

21,500,000

 

 

 

 

 

PC Motorways own funds

Designing: 100% Main Design completed. Preparations for publishing a call for tenders (under the expedited procedure) for selection of a contractor and an engineer that would be published in January 2018. Upon completion of the procedure, signing of contracts and commencement of works is expected in the end of April or the beginning of May 2018.
 

Expropriation: 94%

 

Building: 0%

 

 

 

16

 

 

 

 

MW Tuzla – Žepče

 

 

 

 

55.4

 

 

 

 

60,000,000

 

FBiH Government conclusion – funds from the profit of public enterprises

 

 

Designing: 100%

 

Expropriation: 0%

 

 

Building: 0%

Preliminary Design – Yellow FIDIC. Additional geo-mechanical tests of the 6.2 km long section Tuzla – Lukavac need to be carried out. Preparations for implementation of the tender procedure for selection of a contractor and an engineer for this motorway subsection are in progress. Upon completion of the tender procedure, signing of contracts and commencement of works is planned for the end of 2018.